End-to-End Semantic Accountability & TAMI Project

A first look at project deliverables

project gantt

Key component team v0 v0.1 v.final
REI+ spec:LK, YS, CH 23 July 2007 30 August 2007 29 December 2007*
Scenario development s9: KKW, LD, SH, LK

s4: CH

UI mockup: DJW & HA

23 July 2007 30 August 2007 19 Nov 2007*
Accountability checker (REI+) LK, YS, CH

JH (PAW)

? 30 August 2007 23 May 2008*
Accountability browser JH, CH ? 25 Sept 2008*
Accountability Proxy/log creation CH, JF (security)
integrated architecture CH, JH

JF (security architecture and analysis, as part of evaluation deliverables)

*-contractual commitment


Danny Weitzner
11 July 2007